Linear referencing is the method of storing and geographically locating data using relative positions along a measured line feature. The Forsyth County GIS team previously used this method and kept transportation projects in a linear referencing system (LRS). However, linear referencing was not included in the local government information model that the county adopted.
The GIS and engineering teams are responsible for maintaining different datasets and workflows, but the lack of a linear referencing system meant their two separate databases were not connected. Al Luthringer, GIS database administrator on the Forsyth County GIS team, explains that road asset information created by the engineering team was kept in a separate SQL database that had no spatial component.
Engineering would request maps or reports from the GIS team, which the group would then have to create, but there was no way to sync the two databases together and ensure they had the most up-to-date data. Luthringer says that trying to keep the databases in sync involved a lot of manual work that was very time-consuming.
For example, the engineering department applies to receive funding from the Georgia Department of Transportation for road resurfacing, and the amount is based on the miles of road they maintain. As such, when engineering would request data from the GIS team for their grant application, it would be a rush to prepare everything.
“We were trying to come up with a way to keep these two things in sync because a couple of times a year, we’d be scrambling to try and get the data in their database into GIS because they would need a report or a map,” says Luthringer. “It’s necessary for them to have up-to-date information on what they maintain so that they can get the appropriate funding.”
The lack of synchronization led to data inaccuracies. If the engineering group made a change in data, Luthringer explains, there was no process in place to keep the information in sync and no alerts set up to notify the GIS team that changes were made. The GIS team had to manually look for any differences.
“We didn’t really have the manpower to do that either. It’s just very labor-intensive,” says Luthringer.
Michael Bellino, the GIS manager at Forsyth County, adds that another difficulty was trying to maintain multiple copies of one geometry. The two groups would have different representations of the same roadway characteristics, and keeping everything in sync was a challenge. He says, “There’s a lot of work to get everything back into one common centerline.”
Generating year-end reports for the engineering team also became challenging as more attributes were added to the workflow. Bellino says it took much more time for Luthringer to produce reports because the data took longer—weeks, in some cases—to consolidate.